GuideThe rehab

Schedule the work

See the rehab as a timeline, start from a typical order of work, and let later tasks move when an earlier one slips.

Where it is
A house › Rehab › Board › Timeline
Who can use it
Owners, admins, and team members on the house

The timeline is the same tasks as the board, drawn as bars across the weeks. Switch to it with the Timeline toggle at the top of the board.

Example

Electrical rough-in inspection

locked

Hang drywall, bedrooms

after Electrical rough-in inspection

Install kitchen cabinets

Prime and paint main level

after Hang drywall, bedrooms

Install LVP, upstairs

after Prime and paint main level

The red line is today. Outlined bars are the critical path: the work that sets the finish date.

Three weeks of 1418 Maple Avenue on the timeline.

Start from a template

  1. Step 1: On the timeline, choose Add a schedule template.
  2. Step 2: Pick Cosmetic refresh (4 weeks) or Full gut (8 weeks), or one of your own.
  3. Step 3: Set Work starts.
  4. Step 4: Choose the Add tasks button.
StarterTasksRuns
Cosmetic refresh10, from demo and haul-off to clean and stage28 days
Full gut17, from demo through rough-ins, inspection, drywall, finishes, and final inspections56 days

The tasks land in Scheduled, dated from your start day. Days are calendar days, so weekends count. Rename, re-date, assign, or delete them to fit the job.

Heads upAdding a template never replaces what's there. Add the same one twice and you get every task twice.

Make one task wait on another

  1. Step 1: Open the later task.
  2. Step 2: Under Waits on, choose Choose tasks and tick the work that has to finish first.
  3. Step 3: Choose Done choosing, then Save.

A task starts the day after the last thing it waits on ends. The two starter templates set this up for you.

What happens when something slips

Change a task's dates and everything that waits on it is pushed later by the same amount, and so on down the chain. Each task keeps its length.

  • Dates only move later. Finishing early doesn't pull the rest forward; move those yourself if you want to.
  • A task with no start date is never moved.
  • Tick Keep these dates when earlier work moves to lock a task, such as an inspection the county has already booked. A locked task doesn't move, and neither does work that waits only on it.
  • Moving a card to another column doesn't change any dates.

On the example, the electrical rough-in inspection slipped. If “Hang drywall” waits on it, drywall and everything behind it move with it.

Read the timeline

  • Bars are coloured by status: Scheduled, In progress, Blocked, Done.
  • The red line is today. A red ring marks an overdue task.
  • An outlined bar is on the critical path: the chain of work that sets the finish date. A day lost there is a day lost at the end.
  • Under a task's name, “after” lists what it waits on, and “locked” marks locked dates.
  • Click a bar to open the task. Change dates in the task; bars can't be dragged.

Tasks with no dates aren't shown. The footer counts them.

Print schedule prints the chart at full width. Choose “Save as PDF” in the print window to send it to someone.

Save your own schedule

When a job has gone well, choose Save as template on the timeline and name it. Owners and admins can save templates.

Heads upYour own templates keep each task's name, its place in the order, and how long it takes. They don't keep what waits on what, who it was assigned to, or the room. Set those again on the new house.

Templates and settings covers renaming and deleting templates. To copy a whole house instead, including its budget, see Add a house.